Work on
Bakun dam a year behind schedule
Jun 8,
The RM4.5 billion
2400MW Bakun hydro dam in central
A highly-placed source in the Ministry of Finance-owned company, Sarawak Hydro
Sdn Bhd, disagreed with the ground version that work on the site along the
“It is more than a year behind,” he told malaysiakini
today.
The Bakun project when completed will be able to operate at an average of
1770MW of electricity, originally aimed at the domestic market as well as
The total project cost is estimated at RM4.5 billion, including
the transmission line to
The civil and engineering works, the first part of the project,
have been awarded to a consortium of six Malaysian companies and a mainland
Chinese company, Sino Hydro (
Sime and the other Malaysian companies, including a
The lump sum contract fee is RM1.788 billion with delivery date on
September 2007.
For reasons which have not been officially revealed, China Hydro
took over the project management on the site from Sime Engineering recently,
and officials of Sarawak Hydro, the developer, have told malaysiakini that “the project appears
to be moving,” although there are doubts it could be completed within the
remaining contract period.
Unforeseen factors
The source said the consortium has written to Sarawak Hydro for an
extension of 15 months beyond September 2007 with price variation the main
contractors have claimed as unforeseen factors on the site.
“The Ministry of Finance has yet to make a decision on it,” he
added.
Tied to Bakun in a
proposal put up by various parties, both local and foreign, to set up an
aluminium smelter plant in Bintulu along with a deep-sea port to handle bulk
carriers at Similajau.
Sarawak Chief Minister
Abdul Taib Mahmud recently travelled to China together with businessmen from
Sarawak, including son and CMS Berhad group chairperson Sulaiman Abdul Rahman
Taib, and witnessed the signing of a memorandum of understanding (MoU) between
CMS and two Chinese companies to undertake feasibility studies on the setting
up of a smelter plant in Bintulu using power either from Bakun or even a second
hydro dam nearby at Murun River nearby with half the capacity of Bakun.
The Chinese companies have expertise in aluminium smelter operations, hydro dam
building and port construction.
Government officials, however, said that it is very unlikely that more than one
smelter plant will be approved for Bintulu on environmental grounds.