Extracted from Malaysiakini
Bakun dam more than half-completed
Oct 21,
"We
reached 118-metre elevation yesterday out of the total height of the dam which
is 205 metres," Sime Engineering managing director Mohamad Shukri Baharom
told the New Straits Times.
"We have
2,000 people at the site working 24 hours a day. There are also 700 workers
from
Last month a
report said completion of the dam could be delayed by 18 months, while the
government is to loan millions of dollars to the main contractor to offset
cash-flow problems.
Sources told
the Edge financial weekly
that the government had approved the loan of RM200 million (US$53.05 million)
to "ease the cash-flow situation" for the contractor, a consortium of
seven companies.
Delays and
setbacks
The New Straits Times said that Sime has
set aside RM130 million to cover any potential losses but does not expect to
make more provisions while submissions were made to the government for
reimbursement of cost overruns and an extension of time.
No further
details were available.
The dam
project in eastern
The dam, which involves flooding an area the size of